Planning, Purchasing & Operations
How Much Does Sushi Restaurant Equipment Cost?
One hypothetical limited-menu opening
USD · Worked budget with observed prices and hypothetical inputs. Includes a separate $2,000 reserve.
Inspect the purchased scope ↓In this guide 10 sections +
01 / The cost answer
What does sushi restaurant equipment cost?
In the hypothetical limited-menu opening priced below, the base equipment and opening supplies total about $42,200. Add the specified delivery, site work, care provision, startup, review and tax inputs, plus a $2,000 reserve, and the equipment project’s funding requirement is about $59,000.
A selected addition to an equipped restaurant is a different purchase. So is a set of sushi machines:
Scroll to read the full table →
| Purchase | Cost in the examples below | What the amount covers |
|---|---|---|
| Selected rice, preparation and serving additions | $2,580.80 | A ten-line order relying on refrigeration, washing, work areas and other provision already supplied |
| Limited-menu sushi opening in fitted foodservice premises | $42,207.60 base purchase; approximately $59,000 ready-for-use funding | A defined opening assortment, then explicit additional provision and work; the funding figure includes the $2,000 reserve |
| Selected maki-machine components | $28,800 or $30,000 | Two different sheeting/wrapping/cutting selections, before unpriced options and ready-for-use work |
All amounts are USD. Advertised prices were checked October 13, 2026. The opening combines observed selling prices with clearly identified hypothetical inputs; it is a worked budget, not an ERS project quotation or a national restaurant average.
The figures cover equipment and its readiness for the stated operation. Lease costs, guest furniture, ingredients, preopening payroll and working capital still require separate funding. For the wider equipment and supply scope, use the commercial sushi restaurant guide.
02 / Purchased scope
Two equipment budgets, with the scope shown
Selected additions to an equipped operation
This order assumes the restaurant already has the required refrigeration, sinks, washing, suitable work areas, instruments and remaining service/control provision. The quantities are chosen for the example; they do not establish a seat count or production capacity.
Scroll to read the full table →
| Selected item | Quantity | Advertised unit price | Extension |
|---|---|---|---|
| CUCKOO CR-3032 cooker/warmer | 1 | $250 | $250 |
| I-654-66 hangiri | 1 | $395 | $395 |
| Zojirushi RDS-400 thermal holder | 2 | $310 | $620 |
| IKKAKU MT-90977 yanagiba | 1 | $115 | $115 |
| AG-111 board | 1 | $565 | $565 |
| K1000 stone | 1 | $35 | $35 |
| NC-2 nori container | 1 | $45 | $45 |
| 27-0015 mat | 4 | $0.95 | $3.80 |
| JX288-B plate | 48 | $6.50 | $312 |
| 94027-C geta | 24 | $10 | $240 |
| Selected addition subtotal | $2,580.80 |
That is a useful equipment order. It is not an independent restaurant opening. Other tools, guest utensils, opening supplies and the appropriate care arrangements remain outside it. The wooden serving pieces require a hand-wash route, and the thermal holders require more than storage space between uses.
The independent opening below buys a much broader assortment and explicitly funds the additional care-heating provision in its ready-for-use continuation.
A limited-menu sushi opening in fitted premises
The second example prepares rice, sushi, sashimi and rolls on site for dine-in and takeout. Sealed bottled/canned beverages occupy an assigned protected part of reserve refrigeration. There is no illustrated fryer, grill, hot-entrée or soup line, coffee/tea service, draught system or ice service.
The premises are assumed to retain suitable fixed handwashing, food-preparation, warewashing and mop/service sinks; adequate hot water and building utilities; usable counter support; and appropriate building safety provision. Manual washing and drying must accommodate the selected large hangiri, long board and hand-wash articles. An inherited sink bank is not evidence that every selected object fits its care route.
The example assumes appropriate seafood-supply records and a locally acceptable food-control process. Its ordinary freezer stores frozen inputs; no in-house parasite-treatment or blast-chilling function is credited. It introduces no acidification-validation, vacuum-packaging or extended shelf-life process. Resolve the actual operation through equipment specifications and commercial requirements.
The base equipment and opening-stock purchase
All quantities are assumed. The hypothetical column contains chosen illustration inputs, not quotations or estimates of average market prices. The observed column uses the linked ERS listings and the thermometer manufacturer’s direct price.
Scroll to read the full table →
| Purchased duty | Observed-price extensions | Hypothetical inputs | Illustrative total |
|---|---|---|---|
| Display, reserve and working refrigeration; storage freezer | $0 | $24,000 | $24,000 |
| Rice preparation and holding | $1,515 | $190 | $1,705 |
| Fish/manual preparation and working containers | $1,232.60 | $845 | $2,077.60 |
| Worktables, storage and transport | $345 | $3,200 | $3,545 |
| Dish machine, selected hardware and racks | $0 | $8,150 | $8,150 |
| Instruments and control provision | $78 | $260 | $338 |
| Circulating guest-service assortment | $708 | $588 | $1,296 |
| Opening takeout packaging | $92 | $144 | $236 |
| Opening care and handling provision | $0 | $860 | $860 |
| Base purchase | $3,970.60 | $38,237 | $42,207.60 |
Most of this total is hypothetical. The exact cents preserve the arithmetic; about $42,200 is the appropriate summary. Here is what the groups actually buy.
Cold storage: $24,000. The inputs are one HNC-150BA-L-SLH display case at $7,500, one VR2A-FS reserve refrigerator at $8,000, one VUR27A working undercounter at $4,000 and one VUF27A ordinary storage freezer at $4,500. Display, reserve and working stock have separate assigned provision; a case price does not fund all three.
The ERS HNC case listing requires a quote. Hoshizaki’s October 2, 2026 sheet gives a $7,240 manufacturer list F.O.B. Griffin reference for the HNC-150BA right/left SLH family. That is a different price basis from the hypothetical $7,500 purchase input, not evidence of an ERS selling price or installed amount. Hoshizaki price sheet
Rice preparation and holding: $1,705. Two $250 CR-3032 units, the $395 hangiri and two $310 RDS-400 holders account for $1,515. The $190 hypothetical complement buys two $20 seasoning paddles, two $35 rice-washing bowls, a $50 colander and two $15 seasoning jugs. The cooker’s listed measuring cup, spatula and silicone pad are already supplied; they are not bought again as missing accessories.
Fish/manual preparation: $2,077.60. The observed portion buys two $115 yanagiba, the $565 board, two $35 stones, two $45 nori containers and eight $0.95 mats, plus twelve STPA8134 pans at $17.25 and twelve STPA7130C covers at $5.25. The selected pan-and-cover sets cost $270, not the $207 pan-only amount. These are working containers, separate from factory-supplied case plates.
The $845 hypothetical complement comprises two $80 general-prep knives, two $50 boards, four $30 lidded bins, four $20 bowls, eight $10 hand tools, six $5 squeeze bottles, an $80 scale, four $15 trays, a $35 wrap dispenser and a $100 tool-storage/non-slip-accessory lot.
Worktables, storage and transport: $3,545. This combines the observed $345 C-3222 cart with two hypothetical $1,200 all-stainless 30 × 60-inch tables with undershelves and two $400 complete four-tier shelving units. The table inputs describe a generic configuration to quote; they are not prices attributed to the quote-only GSW worktable selection.
Washing: $8,150. The hypothetical purchase is $6,500 for a CMA UC50e, $1,000 for matched treatment hardware/initial media, $500 for selected drain-water tempering hardware and $150 for three additional compatible racks. The maker’s specification includes the machine’s booster, chemical pumps and one standard rack. Those supplied components are not added again. Actual treatment/tempering selection and building services still need confirmation. CMA UC50e and documentation
Instruments and control provision: $338. Two selected ThermoPop 2 TX-3120-RD probes at $39 contribute the observed $78. The $260 hypothetical complement buys four $20 cabinet thermometers, two $20 timers, two $15 label rolls, $10 probe-check supplies, $50 high-temperature warewashing indicator stock, $20 compatible sanitizer strips and two $15 record supports. This prices the selected provision; it does not establish approval of a food process.
Guest service: $1,296. Seventy-two $6.50 plates and twenty-four $10 geta contribute $708. The hypothetical $588 complement buys seventy-two $2 sauce dishes, seventy-two $1 reusable chopstick pairs, forty-eight $3 drinking vessels, twenty-four $3 guest utensil sets, twelve $8 soy dispensers and four $15 service trays. These quantities describe an assortment, not the correct circulation stock for a stated seat count.
Opening takeout stock: $236. Eight ED-05 packs at $11.50 buy 400 tray/lid sets for $92. The hypothetical $144 complement buys 400 bags at $0.12, 400 sauce-cup/lid sets at $0.08, 400 wrapped chopstick pairs at $0.06, 1,000 napkins at $0.02 and 400 labels at $0.05. The tray price alone is not the complete packaging cost of an order.
Opening care/handling: $860. The hypothetical stock comprises two $50 waste receptacles, four $20 bus tubs, $60 handwash dispensing/startup provision, $150 dish-machine detergent/rinse-aid stock, $100 compatible cleaner/sanitizer/film stock, $100 towels/brushes, two $15 glove boxes, $50 bin liners, six $15 aprons and $100 floor-cleaning tools. These are opening purchases, not annual consumption estimates.
The base list still needs the $900 care-heating provision and the delivery/site work priced below. Guest furniture, décor, unrelated POS/IT, lease acquisition, ingredients, preopening payroll, marketing and working capital remain outside this equipment example. Required equipment supports or interfaces cannot be removed merely by classifying them as décor or technology.
Use the complete equipment and supplies checklist to build the actual order, then select quantities against the real workload and capacity requirement.
Cold storage
- Display refrigeration
- Reserve refrigeration
- Working refrigeration
- Ordinary frozen storage
Rice & preparation
- Rice cooking & holding
- Manual preparation
- Working containers
Support & care
- Worktables, storage & transport
- Washing & control provision
- Manual wash & dry route
Fixed sinks · hot water · suitable utility services · counter support
Illustrative duty groups, not a floor plan. The dishwasher does not replace manual washing and drying for the large hangiri, long board and hand-wash articles. The additional $900 care-heating provision follows in the readiness budget. No hot-menu line or parasite-treatment freezer function is credited.
Explore the ERS collection
Commercial Rice Cookers & Warmers
Compare the assortment for this part of your service.
-
Image unavailable
Hattori Natural Gas Deck Rice Cooker, 3-Deck, 21 kg - LG-000-150
View details & options ↗: Hattori Natural Gas Deck Rice Cooker, 3-Deck, 21 kg - LG-000-150
-
Image unavailable
Hattori Natural Gas Deck Rice Cooker, 2-Deck, 14 kg - LG-000-100
View details & options ↗: Hattori Natural Gas Deck Rice Cooker, 2-Deck, 14 kg - LG-000-100
-
Image unavailable
Rinnai Commercial Natural Gas Rice Cooker, 55-Cup - RER-55AS
View details & options ↗: Rinnai Commercial Natural Gas Rice Cooker, 55-Cup - RER-55AS
-
Image unavailable
CUCKOO Commercial Rice Cooker & Warmer, 30-Cup - CR-3032
View details & options ↗: CUCKOO Commercial Rice Cooker & Warmer, 30-Cup - CR-3032
-
Image unavailable
Zojirushi Commercial Electric Rice Warmer, 8L (44-Cup) - THA-803S
View details & options ↗: Zojirushi Commercial Electric Rice Warmer, 8L (44-Cup) - THA-803S
-
Image unavailable
Tiger 3-Cup Rice Cooker & Warmer, Floral White - JNP-0550-FL
View details & options ↗: Tiger 3-Cup Rice Cooker & Warmer, Floral White - JNP-0550-FL
-
Image unavailable
Zojirushi Commercial Thermal Rice Warmer, 4L (22-Cup) - RDS-400
View details & options ↗: Zojirushi Commercial Thermal Rice Warmer, 4L (22-Cup) - RDS-400
-
Image unavailable
Zojirushi Commercial Thermal Rice Warmer, 6L (33-Cup) - RDS-600
View details & options ↗: Zojirushi Commercial Thermal Rice Warmer, 6L (33-Cup) - RDS-600
Review options, order units and current availability on the product page.
03 / Format & menu
How the restaurant format changes the budget
Full-service sushi with a hot menu
Adding tempura, grilling or other cooked-menu work changes the appliance order, preparation/holding provision and applicable utility, ventilation and fire-protection work. A retained usable hot line and a space needing a new installation are different projects, even when both restaurants are described as full-service.
Price those actual additions. An arbitrary percentage applied to the $42,200 base does not specify the cooking equipment or its site requirements. The small care-heating allowance in this example also does not fund a hot-food menu. Define that program through the full-service sushi restaurant guide.
Omakase and chef’s counters
A smaller seat count can still require substantial counter fabrication, reserve/display provision and a carefully chosen tool and presentation assortment. The service sequence determines circulating ware and its return-to-use requirement. It does not follow a universal equipment-cost-per-seat allowance.
An exact tool choice makes the difference concrete. Substituting one $470 Masamoto KK0424 for one $115 MT-90977 increases that selected purchase by $355 before freight and tax. These are different knives, with different lengths, construction and care. The arithmetic does not make the substitution an equivalent-performance bargain or a required omakase upgrade.
Specify the chef’s-counter operation, then price its actual counter, refrigeration, cutlery and presentation choices.
Express and fast-casual
An express purchase can move capital toward task-specific automation and pack-out. It still needs prepared rice, ingredients, cold storage, loading, filling, finishing and care. Buying forming or cutting equipment does not automatically remove any of those obligations.
The machine combinations below provide inspectable component prices. The complete-order packaging example later shows a recurring cost that a tray-only price conceals. Fast-casual and express planning establishes the operating requirement; the cost comparison must retain the work surrounding the machines.
Kaiten and direct-to-table service
A custom service system needs a project scope. AUTEC describes configurable conveyor layouts and a monorail arrangement with ordering interfaces, but its inspected public pages do not provide a usable installed price or universal recurring fee. Conveyor description, monorail description
The priced offer should settle route hardware and supports, table/service interfaces, controls and ordering connections, serving/return articles, installation, startup, cleaning/support access and any actual continuing obligations. Mention of a feature does not establish whether it is included, optional or separately charged.
Keep food production, refrigeration and clean return in the restaurant budget. Transport does not supply those functions. Use the kaiten restaurant guide for the operating format and the automated-service equipment guide for mechanism/configuration detail. No generic cost per foot or seat substitutes for that coordinated purchase.
Central and host-provided support
Allocated upstream preparation, storage, washing or beverage service can remove specific local purchases. It can also leave service, access, transport or upstream costs. The local equipment order should reflect the provision actually supplied, not an assumed free subsidy.
That is why the $2,580.80 addition cannot be treated as a low-cost standalone opening: it does not value everything supporting it. For a program inside another operation, establish the host-supported provision before comparing new local spending.
04 / Automation
What sushi automation adds to the equipment bill
Price the functions together. A rice sheeter, manual wrapper and cutter purchase is different from an integrated sheeter/wrapper plus cutter:
Scroll to read the full table →
| Selected arrangement | Observed component arithmetic | Subtotal |
|---|---|---|
| Separate sheeting, manual wrapping and cutting | ASM895A $17,500 + ASA190A $3,800 + ASM260A $7,500 | $28,800 |
| Integrated sheeting/wrapping plus cutting | ASM890A $22,500 + ASM260A $7,500 | $30,000 |
| First arrangement plus cooked-rice mixing | $28,800 + ASM730A $12,800 | $41,600 |
| Second arrangement plus cooked-rice mixing | $30,000 + ASM730A $12,800 | $42,800 |
Selected component-price sums · USD · observed October 13, 2026
ASM730ACooked-rice mixing$12,800Add $12,800 for cooked-rice mixing: $41,600 or $42,800 respectively.
Cooking, holding, hand filling and final completion remain separate operations.
Required options, tooling and ready-for-use work remain unpriced. These selections are not complete installed lines and do not establish equal menu capability, output or staffing.
These are selected component-price sums, before unpriced required options and ready-for-use work. The $1,200 difference between the first two does not establish equivalent menu capability, throughput or staffing.
The ASA190A retains manual lever operation. The integrated unit changes the sheeting/wrapping work, while filling and final completion remain. The ASM730A mixes cooked rice; its purchase does not buy cooking, receiving or the working support around it. AUTEC manual wrapper, integrated unit, mixer
Compatibility also has a purchase consequence. AUTEC gives the wrapper an approximately 20–60 mm roll-diameter envelope, while its ASM260A page gives 24–50 mm. The common diameter envelope is narrower than the wrapper’s range; roll length and selected cutter unit must also match. Listing available wrapping or cutter units does not establish that all are included in the advertised price. AUTEC cutter specifications
Before treating either arrangement as a complete configured purchase, settle the included tooling, required options, receivers, worktop/support, operating access, cooking/holding provision, freight, tax, connections, instruction and opening operating supplies. Identify what already exists and what is genuinely displaced. Do not automatically deduct the hangiri, manual tools, refrigeration or downstream labor from the base opening.
Use the sushi-machine guide to distinguish functions and the ERS robot selection to inspect models. The financial return depends on the actual work and cash changed, evaluated separately below.
Explore the ERS collection
Sushi Robots & Sushi Machines
Compare the assortment for this part of your service.
-
Image unavailable
Autec Maki Sushi Maker Rice Sheeter ASM895A
View details & options ↗: Autec Maki Sushi Maker Rice Sheeter ASM895A
-
Image unavailable
AUTEC Maki Sushi Maker Rice Sheeter & Wrapper ASM890A
View details & options ↗: AUTEC Maki Sushi Maker Rice Sheeter & Wrapper ASM890A
-
Image unavailable
AUTEC Maki Sushi Roll Wrapper ASA190A
View details & options ↗: AUTEC Maki Sushi Roll Wrapper ASA190A
-
Image unavailable
AUTEC Automatic Maki Sushi Roll Cutter ASM260A
View details & options ↗: AUTEC Automatic Maki Sushi Roll Cutter ASM260A
-
Image unavailable
AUTEC Nigiri Sushi Maker Rice Ball Shaper ASM440A
View details & options ↗: AUTEC Nigiri Sushi Maker Rice Ball Shaper ASM440A
-
Image unavailable
AUTEC Onigiri & Musubi Rice Ball Maker ASM575A
View details & options ↗: AUTEC Onigiri & Musubi Rice Ball Maker ASM575A
-
Image unavailable
AUTEC Shari Sushi Rice Mixer ASM730A
View details & options ↗: AUTEC Shari Sushi Rice Mixer ASM730A
-
Image unavailable
AUTEC Shari Sushi Rice Mixer ASM780A
View details & options ↗: AUTEC Shari Sushi Rice Mixer ASM780A
Review options, order units and current availability on the product page.
05 / Readiness & reserve
From equipment subtotal to ready-for-use cost
The original $42,207.60 purchase is only the starting point for the same fitted-premises opening. The following continuation assigns the work and provision needed to make it usable.
All added dollar inputs are hypothetical. Each allowance includes its associated materials and applicable tax. The separate purchase-tax line applies only to the original assumed taxable purchase base.
Scroll to read the full table →
| Cost entry | Amount | Scope in this example |
|---|---|---|
| Base equipment/opening-stock purchase | $42,207.60 | The complete base schedule above |
| Freight | $1,500 | No storage, repeated delivery or unusual route |
| Receiving/unloading/inside placement | $800 | Accessible ground-floor placement; no crane or stair carry |
| Assembly, leveling, minor support/sealing | $600 | Suitable retained counter foundation; no new custom counter |
| Minor electrical work/final connection | $1,500 | Suitable existing service/panel; limited work and selected connections |
| Plumbing/drain/treatment connections | $1,800 | Accessible retained hot water/drainage; hardware already purchased stays in the base |
| Startup/checks/instruction | $600 | Initial readiness; opening chemicals already purchased |
| Limited drawings/equipment-related review/inspection | $2,500 | No major redesign; not the entire business permit budget |
| Unpacking waste/final setup cleaning | $250 | No old-equipment demolition/removal |
| Additional care-heating provision | $900 | Appliance, compatible vessel and handling tools; connection included in electrical work |
| Added work/provision subtotal | $10,450 | Hypothetical inputs |
| Purchase-tax planning line | $4,326.28 | $42,207.60 × 10.25%, rounded once |
| Identified ready-for-use inputs | $56,983.88 | Approximately $57,000 before reserve |
| Separate reserve | $2,000 | Minor within-scope adjustments/another visit |
| Funding provision including reserve | $58,983.88 | Approximately $59,000 |
Hypothetical limited-menu opening in fitted premises · USD. Tax is applied once to the assumed taxable original purchase; other allowances include their associated tax. Lease and working capital remain separate.
The reserve is funding kept available, not an expense already incurred. A known panel replacement, larger hot-water system, drain trench, new ventilation/fire-protection installation or counter reconstruction is a changed scope, not a small contingency item.
Why the site lines matter
The HNC case requires appropriate support, airflow, electrical and drainage provision. A case that fits visually on a counter can still need work before use. Its supplied plates and drain hose are already included, so the site schedule does not buy them again. Hoshizaki HNC installation instructions
The UC50e’s built-in booster does not establish that any inherited hot-water supply is adequate. Its specified electrical and incoming-water provision must be accommodated. The original $1,000 treatment hardware, $500 tempering hardware and additional racks remain equipment purchases; the plumbing line connects the selected provision. Startup uses the opening chemical stock. CMA UC50e specification
The $900 care-heating allowance closes another specific duty. Zojirushi’s instructions require boiling-water care of the RDS removable sponge as well as preheating and manual cleaning. Ordinary dishwashing hot-water provision alone does not establish that method. The allowance includes a suitable appliance, compatible vessel and handling tools; its electrical connection is counted once in the electrical line. Confirm the actual equipment, location, utilities and applicable review. It does not fund a hot-menu line or establish a ventilation exemption. Zojirushi RDS instructions
Tax, review and included work
The tax calculation uses the Los Angeles city rate of 10.25% effective October 1, 2026, with the entire original purchase assumed taxable for planning. Check the actual destination, item and invoice treatment. Other project allowances already include their associated tax; applying another blanket percentage to them would double count that assumption. CDTFA city/county rates
Delivery and installation/fabrication charges do not all receive identical treatment. California’s guidance sets conditions for delivery charges and distinguishes installation labor from fabrication. CDTFA delivery guidance, labor guidance
The $2,500 review/drawing amount is a chosen combined allowance, not a published fee for this unlocated project. Replace it and the other allowances with actual scoped quotations. If an installer bundles placement, assembly and startup, map the included tasks and remove duplicate rows. If a quote omits them, they remain costs to fund. Detailed site and control decisions belong in commercial requirements.
06 / Purchase choices
Where to reduce the purchase without leaving gaps
Retain equipment when it can perform the required duty and the cost to keep it usable is preferable to replacing it. Price a used unit as a complete initial acquisition, including assessment, restoration, missing parts, movement and startup.
This entirely hypothetical, like-duty display-case comparison is before tax, financing and ongoing costs:
Scroll to read the full table →
| Initial cost | New case | Used case | Retain suitable installed case |
|---|---|---|---|
| Acquisition | $7,500 | $3,000 | $0 |
| Assessment | Included in new startup scope | $200 | $200 |
| Cleaning/restoration/missing parts | Complete new unit | $900 | $600 |
| Freight | $500 | $500 | $0 |
| Placement/startup | $300 | $300 | $0 incremental relocation |
| Initial subtotal | $8,300 | $4,900 | $800 |
Used reduces initial outlay by $3,400 and retention by $7,500 on those assumptions. At $4,300 of used-unit restoration, the initial-cost advantage disappears before any ongoing difference is considered. No standard used-equipment discount, remaining life or repair frequency is assumed.
The retained case is assumed appropriate, already installed and complete after restoration. For a real project, change the purchase line, applicable tax and only the site tasks actually avoided. Keeping one refrigerator does not eliminate shared work for the remaining equipment. These comparison allocations are not extra charges in the opening budget above.
Coverage also matters. Hoshizaki’s display-case warranty is limited to the original owner/user and is nonassignable; its exclusions include travel/premium labor and consequential commercial losses. Those particular terms are not a warranty statement for every refrigerator. Hoshizaki display-case warranty
A lower purchase price cannot compensate for the wrong duty, incompatible configuration or missing support. Use supplier and offer evaluation for the actual offer and care/restoration planning for the work needed to return it to use.
Optional automation can be staged while the manual opening remains properly provided. Keep cold storage, washing, care and controls funded. Identify later freight, repeat mobilization, connection, training and disruption rather than assuming a deferred purchase will cost only the later machine price. A reserved footprint does not require buying the machine now, and early purchase does not guarantee indefinitely deferred warranty coverage.
07 / Operating expense
What the equipment costs to run and maintain
Test the operating difference against the purchase premium
For a selected working-undercounter comparison, Hoshizaki lists 0.95 kWh/day for VUR27A and 0.651 kWh/day for UR27B, both labeled at ASHRAE conditions. Their AHAM capacities are 6.33 and 6.21 cubic feet; construction and published coverage also differ. These are not declared identical specifications. VUR27A sheet, UR27B sheet
Assume five years, 365 days/year and $0.25/kWh, with hypothetical acquisition inputs of $4,000/$7,000 and equal $400 readiness amounts:
Scroll to read the full table →
| Selected five-year cost | VUR27A illustration | UR27B illustration |
|---|---|---|
| Hypothetical purchase | $4,000 | $7,000 |
| Hypothetical delivery/placement/startup | $400 | $400 |
| Electricity from published test consumption at assumed rate | $433.44 | $297.02 |
| Purchase + readiness + electricity | $4,833.44 | $7,697.02 |
The energy difference is about $136 over five years, against a $3,000 hypothetical acquisition premium. On this limited basis, the higher-purchase illustration remains $2,863.58 higher. Other advantages may justify the specification, but the test-energy difference alone does not recover that premium.
These are selected-cost subtotals, not full lifetime costs. Tax, financing, cleaning, service, repair, interruption, disposal and resale are outside them. Five years is a comparison period, not a lifespan forecast. Actual door use, loading, room conditions and the utility’s full tariff can change operating expense; the published test figure is not a measured restaurant bill.
Price all the packaging the order uses
The observed ED-05 price is $11.50 for fifty tray/lid sets, or $0.23/set. For one hypothetical single-tray order, the original companion inputs produce:
Scroll to read the full table →
| Packaging component | Assumed use/order | Cost/order |
|---|---|---|
| ED-05 tray/lid set, observed price | 1 | $0.23 |
| Bag, hypothetical price | 1 | $0.12 |
| Sauce cup/lid, hypothetical price | 1 | $0.08 |
| Wrapped chopstick pair, hypothetical price | 1 | $0.06 |
| Napkin, hypothetical $0.02 each | 2 | $0.04 |
| Label, hypothetical price | 1 | $0.05 |
| Assumed complete packaging | $0.58 |
The source ED-05 pack contains fifty tray/lid sets for $11.50. Shapes are illustrative; fit has not been verified. Food contents, packing labor, freight and tax are excluded.
The order format must actually fit those pieces. Multiple trays, extra sauces, more utensils or beverage packaging change the cost. Contents, packing labor, freight and tax are not included.
At a hypothetical 100 such orders/day for 300 days, consumption is $17,400/year: $6,900 for tray/lid sets and $10,500 for the other assumed pieces. The opening purchase already contains $236 of stock. With unchanged prices, all that stock usable, no waste and no ending safety stock, later first-year purchases are $17,164, not another $17,400.
Deduct the actual inventory by component: the opening has 400 of each single-per-order article but 1,000 napkins. The subsequent tray/lid purchase is 29,600 sets, or 592 fifty-set packs. Real order multiples and target closing stock change cash purchasing; use the ongoing supply guide for that replenishment work.
Keep care, water and interruption in the comparison
An unpowered thermal holder still consumes preheating water/heat and care time. Water-treatment hardware still requires its actual media/regeneration provision. Initial chemical stock is not an annual chemical budget, and a replacement-part price is not a failure forecast.
The UC50e manual illustrates why a per-rack figure is incomplete: it lists 0.8 gallon/rack alongside a 6.87-gallon tank and describes tank-water replacement. It also gives booster-heater priority over wash-tank heating. Summing both heater ratings and multiplying by every open hour would not describe that controlled operation. CMA UC50e manual
For a washing comparison, collect comparable wash/idle energy, water, incoming-water requirements, dosing, treatment and care inputs. EPA’s commercial-dishwasher discussion separates these metrics; it does not establish this selected unit’s actual restaurant savings. ENERGY STAR dishwasher metrics
Likewise, the $22.50 AUTEX 8 fl. oz. trigger bottle establishes a purchase unit, not annual consumption. Price compatible supplies against actual use.
Warranty does not make interruption free. Compare uncovered service and non-overlapping fallback costs, discarded stock and foregone contribution after avoided costs. Do not treat all lost sales as profit lost or invent an annual outage frequency. Maintenance, cleaning and parts planning supplies the detailed care/support requirements; the budget carries their money consequences.
Explore the ERS collection
Sushi To-Go Containers
Compare the assortment for this part of your service.
-
Image unavailable
Kamon Sushi To-Go Tray with Lid (50 pc) - YP-2.0, 9"
View details & options ↗: Kamon Sushi To-Go Tray with Lid (50 pc) - YP-2.0, 9"
-
Image unavailable
Long Kamon Sushi To-Go Tray with Lid (50 pc) - YP-0.6, 8-5/8"
View details & options ↗: Long Kamon Sushi To-Go Tray with Lid (50 pc) - YP-0.6, 8-5/8"
-
Image unavailable
Kraft Paper Sushi To-Go Tray with Clear Anti-Fog Lid (600 pc) - PH-09
View details & options ↗: Kraft Paper Sushi To-Go Tray with Clear Anti-Fog Lid (600 pc) - PH-09
-
Image unavailable
Kamon Sushi To-Go Container with Clear Lid (50 pc) - Large 10-1/2" x 7-3/4"
View details & options ↗: Kamon Sushi To-Go Container with Clear Lid (50 pc) - Large 10-1/2" x 7-3/4"
-
Image unavailable
Long Black Sushi To-Go Tray with Clear Lid (50 pc) - ED-30B, 9-1/4"
View details & options ↗: Long Black Sushi To-Go Tray with Clear Lid (50 pc) - ED-30B, 9-1/4"
-
Image unavailable
Sushi To-Go Tray with Clear Lid (100 pc) - Large Red & Silver
View details & options ↗: Sushi To-Go Tray with Clear Lid (100 pc) - Large Red & Silver
-
Image unavailable
Sushi & Bento To-Go Tray with Clear Lid (100pc) - Small Red & Silver
View details & options ↗: Sushi & Bento To-Go Tray with Clear Lid (100pc) - Small Red & Silver
-
Image unavailable
Kamon Sushi To-Go Tray with Clear Lid (50 pc) - ED-03 / YP-0.8
View details & options ↗: Kamon Sushi To-Go Tray with Clear Lid (50 pc) - ED-03 / YP-0.8
Review options, order units and current availability on the product page.
08 / Return on investment
When automation pays for itself
Use the complete incremental cost and the cash benefit that actually changes. The following is a separate unnamed hypothetical intervention, not an installed quote for either machine selection above:
- $36,000 ready-for-use investment.
- 300 operating days/year.
- $28 per genuinely avoidable paid hour.
- $1,800/year additional operating expense.
Scroll to read the full table →
| Net avoidable paid hours/day | Annual avoided paid cost | Annual net benefit after added expense | Simple payback |
|---|---|---|---|
| 0 | $0 | −$1,800 | No positive payback on this basis |
| 1 | $8,400 | $6,600 | About 5.45 years |
| 2 | $16,800 | $15,000 | 2.4 years |
Hypothetical unnamed intervention · annual net benefit after added expense
- Investment
- $36,000
- Operating days / year
- 300
- Avoidable paid hour
- $28
- Added expense / year
- $1,800
Net avoidable paid hours per operating day. No positive payback at zero hours; about 5.45 years at one hour; 2.4 years at two hours. The alternative additional-order case is separate.
Net paid hours come after loading, replenishment, transfer, finishing, changeovers, cleaning and other retained or added work. If the same person works the same paid shift but spends less time forming rice, there is no payroll-cash reduction from that change alone. Demonstrably avoided overtime, additional shifts or planned hiring can count on their actual cost and timing.
The $28 input means cost genuinely removable or avoidable, not automatically the stated wage plus every allocated employment expense. A fixed cost does not disappear because it was assigned to an hour. Use the workflow and capacity analysis to establish the net task/resource change before converting it into a labor-cost claim.
For a chosen five-year simple-payback target, these inputs require about 1.07 avoidable paid hours/day. One hour gives the 5.45-year result shown; it does not meet that particular target. The target is a purchasing assumption, not a recommended cutoff or equipment-life prediction.
Additional sales are a different benefit. In an alternative hypothetical case, the same intervention removes no paid hours but enables five additional completed, sold orders/day, each contributing $8 after order-variable costs. Across 300 days that is $12,000 contribution, or $10,200 after the $1,800 operating increment: approximately 3.53-year simple payback.
That contribution must be after ingredients, packaging, payment/platform fees and any variable labor. Demand must exist, and the remaining production and handoff must fulfill it. Do not add the one-hour case’s $8,400 saving to the same redeployed-time case without evidence of a separate feasible staffing change.
These simple-payback cases are undiscounted and exclude financing, buyer-specific tax benefits, resale and an assumed failure pattern. Equipment can have business value without payroll savings. Quality, service or contribution must then support their own case rather than borrow an invented labor benefit.
09 / Funding & timing
Buying outright, financing and cash before opening
The same $56,983.88 ready-for-use scope can require cash well before it is operating. Here is one hypothetical payment allocation, not ERS, manufacturer or contractor terms:
Scroll to read the full table →
| Assumed milestone | Payment | Cumulative paid |
|---|---|---|
| Order/approved-scope commitment | $19,700 | $19,700 |
| Before delivery/procurement | $33,683.88 | $53,383.88 |
| Placement/completion/startup | $3,600 | $56,983.88 |
| Separate reserve held available | $2,000 | $58,983.88 total funding provision |
The allocation assumes a half-deposit on the original $30,500 refrigeration/dishwasher group, the $2,500 review allowance and half of the $3,900 assembly/electrical/plumbing work at commitment. Before delivery it pays the equipment balance, remaining $11,707.60 base purchase, purchase-tax allowance, freight and $900 care provision. The final phase covers placement, the site-work balance, startup and unpacking cleanup.
Every earlier amount is counted once. More than $53,000 has been paid before placement/startup finishes in this illustration. A small final invoice does not mean a small opening cash commitment; working capital remains additional.
Even if a hypothetical funding arrangement covered all $30,500 of those five major equipment lines, $26,483.88 of other identified inputs, or $28,483.88 including reserve, would need another funding source. That does not establish equipment eligibility, a zero down payment or absence of fees.
Read the actual agreement for funded scope, upfront cash/fees, installment count and amount, required final payment or ownership decision, mandatory continuing charges and termination/payoff obligations. Count each obligation once. A repayment total already containing equipment principal does not receive another full acquisition-principal charge. Track refundable deposits separately under their actual return conditions.
AUTEC has a payment-plan inquiry route, but it does not establish this buyer’s rate, term, fees, approval, ownership outcome or an ERS financing program. No buyer-specific tax saving is included in these examples. Compare the actual written offer through the supplier and offer evaluation guide.
10 / From budget to purchase
Get a scoped equipment budget from ERS
Bring ERS the restaurant you intend to operate: its format and menu, workload requirement, location and target date, retained equipment/services, selected new functions and quantities, and the options that must remain compatible. For replacement, identify the existing unit and interfaces. For automation, identify the task being changed.
Separate settled selections from items needing advice or quotation. State the delivery access and the freight, placement, connection/startup or other work that the offer must address. A schedule with observed prices, assumptions and quote-dependent items identified gives the equipment conversation a usable starting point.
ERS has supplied Japanese restaurants from Los Angeles since 2002. Use that equipment and supply experience to define the purchase, then confirm the priced scope and expressly included work. Contact ERS about the equipment requirement.




